<del id="bbhtt"></del>
<progress id="bbhtt"><video id="bbhtt"></video></progress>
<listing id="bbhtt"></listing><listing id="bbhtt"><video id="bbhtt"></video></listing><del id="bbhtt"><strike id="bbhtt"><cite id="bbhtt"></cite></strike></del>
<i id="bbhtt"><video id="bbhtt"><ins id="bbhtt"></ins></video></i>
<i id="bbhtt"></i>
<thead id="bbhtt"><span id="bbhtt"></span></thead>
<i id="bbhtt"></i>
<listing id="bbhtt"></listing>
<listing id="bbhtt"><video id="bbhtt"></video></listing>
<i id="bbhtt"><video id="bbhtt"><ins id="bbhtt"></ins></video></i><listing id="bbhtt"></listing>
<i id="bbhtt"><video id="bbhtt"><ins id="bbhtt"></ins></video></i><del id="bbhtt"><strike id="bbhtt"><var id="bbhtt"></var></strike></del>
<del id="bbhtt"><strike id="bbhtt"><cite id="bbhtt"></cite></strike></del>
<del id="bbhtt"><strike id="bbhtt"><cite id="bbhtt"></cite></strike></del>
<i id="bbhtt"><video id="bbhtt"><del id="bbhtt"></del></video></i>
<thead id="bbhtt"><span id="bbhtt"></span></thead>
<listing id="bbhtt"><video id="bbhtt"></video></listing>
RecruitmentHome · News ·
柬埔寨達岱水電站2#機組成功并網發電
Published:2014/9/5

  柬埔寨時間2014年9月4日18時達岱水電站2#機組順利通過72小時試運行。
  達岱水電站2#機組從技術供水管路充水到機組首次手動開機完成各項調試試驗緊用6天時間,在這期間各相關單位加班加點、緊密配合使機組于8月22日一次并網成功并完成機組甩負荷試驗。由于當地電網負荷比較小,只能在1#機組完成72小時試運行后2#機組才能滿負荷運行,目前3#機組的各項試驗已完成并初次并網成功負荷帶到40MW運行4小時,計劃下周進入并網滿負荷試運行。


 